PLANNING COMMISSION
Minutes of the
September 12, 2005 Meeting
Meeting #817 of the Hanover Township Northampton County
Planning Commission was held at the
Planning Commission members in attendance:
Mark Tanczos Joseph Hilton
Paul Kuehne John McGonigle
Susan Lawless George Scoggin
Glenn Taggart
Hanover Engineering Associates, Inc. represented by Charles M. Schmalzer, P.L.S.
Motion was made by Taggart, seconded by Hilton, approving
the minutes of the
Hilton, yes; Kuehne, yes; McGonigle, yes; Lawless, yes; Taggart, yes; Scoggin, abstain; Tanczos, yes
DEWIRE ESTATES Subdivision Plan Preliminary/Record Plan
James Holzinger, Esq. (Attorney) Richard Shelly (Martin, Bradbury & Griffith)
Dewire (Developer)
Comments outlined in letter from Hanover Engineering,
dated
Holzinger advised developer’s
agreement with the City of
Holzinger stated he talked with Township resident James Ravelle. The City was asked to inform Ravelle when construction would take place.
Grading and Utilities Plan indicates a 6” PVC pipe
connection to an existing 4” main on
Lot Line Adjustment Plan (Kingston Tract) has not been recorded. Attorney Piperato has been contacted regarding this matter.
Section 159-17.F.2.(c) - Developer will offer a cash contribution for replacement trees.
Section 159-23.B.(1) - Developer will show electric and gas utilities for proposed subdivision.
Section 159-29.C.(6).(a) - Developer provided a chart listing the types of existing trees on this property. The total number of trees has not been designated, nor the trunk diameter. Upon discussion, Planners requested that every tree be numbered on a separate sheet (Tree Location Plan), which can be cross referenced with the provided tree chart. This added sheet should be color coded, indicating the trees to be removed and the trees remaining. The Township needs to catalog the trees that will be removed (in right of way, for swales, in easements), as well as the trees that will remain.
Motion was made by Tanczos, seconded by Kuehne, recommending that a tree numbering plan, that can be cross referenced with current tree chart, be provided, instead of listing the trunk diameters of existing trees.
Hilton, yes; Kuehne, yes; McGonigle, yes; Taggart, yes; Lawless, yes; Scoggin, yes; Tanczos, yes
Soil Erosion Control Plan approval, LVPC approval and N.P.D.E.S. Permit is required.
Proposed street lighting must be approved by the Township Manager.
Motion was made by Tanczos, seconded by Kuehne, to
send a letter to the Board of Supervisors, recommending Conditional Approval
pending satisfaction of comments made in Hanover Engineering’s letter dated
Hilton, yes; Kuehne, yes; McGonigle, yes; Taggart, yes; Lawless, yes; Scoggin, yes; Tanczos, yes
ENGINEER’S REPORT
Curb and sidewalk will be
installed along
Major construction on
Road work remains on
Sylvia McLaughlin - Clerk