Gaspar Ave & Kim St. Stormwater Project
Hanover Township will begin a storm sewer installation project along Gaspar Avenue and Kim Street in early May.
The Township placed this project out for bid in the winter and is using grant money that is remaining to help fund this project. Traffic disruptions are expected on Gaspar Avenue during construction.
Please use alternate routes when possible. Residents will have access to their homes but may experience minor inconveniences when work is occurring in front of their property.

Contractor - Charlie Nansteel, LLC
Any questions about this project contact Chad Nansteel - Site Manager (610)597-9751
Current Schedule as of 04/30/2026
|
May 4 - May 8, 2026 |
Tree removal and street saw cutting along Gaspar Ave and Kim St. |
|
May 11 - July 10, 2026 |
Install storm inlets, piping and relocate water mains |
|
July 13 - July 24, 2026 |
Trench pavement restoration |
|
July 27 - July 31, 2026 |
Vertical curb installation |
|
August 3 - August 10, 2026 |
Driveway restoration |
|
August 10- August 1, 2026 |
Lawn restoration and tree installation |
|
August 14 - August 21, 2026 |
Full width pavement restoration |
|
August 24 - August 28, 2026 |
Final clean up |
|
|
|
**During vertical curb installation and driveway restoration work, your driveways will have limited to no access.
We will notify which houses this will be affecting beforehand. As of this letter our target date is July 27 - August 10, 2026.
***All dates are subject to change. We will notify you of any significant changes to this schedule.