Gaspar Ave & Kim St. Stormwater Project


Hanover Township will begin a storm sewer installation project along Gaspar Avenue and Kim Street in early May.
The project will continue through September and is intended to improve stormwater drainage in the area.
The Township placed this project out for bid in the winter and is using grant money that is remaining to help fund this project.  Traffic disruptions are expected on Gaspar Avenue during construction.
Please use alternate routes when possible. Residents will have access to their homes but may experience minor inconveniences when work is occurring in front of their property.  

Contractor - Charlie Nansteel, LLC 
Any questions about this project contact Chad Nansteel - Site Manager (610)597-9751

Current Schedule as of 04/30/2026

May 4 - May 8, 2026

Tree removal and street saw cutting along Gaspar Ave and Kim St.

May 11 - July 10, 2026

Install storm inlets, piping and relocate water mains

July 13 - July 24, 2026

Trench pavement restoration

July 27 - July 31, 2026

Vertical curb installation

August 3 - August 10, 2026

Driveway restoration

August 10- August 1, 2026

Lawn restoration and tree installation

August 14 - August 21, 2026

Full width pavement restoration

August 24 - August 28, 2026

Final clean up

 

 

**During vertical curb installation and driveway restoration work, your driveways will have limited to no access.

We will notify which houses this will be affecting beforehand. As of this letter our target date is July 27 - August 10, 2026.

***All dates are subject to change. We will notify you of any significant changes to this schedule.

Hanover Township

3630 Jacksonville Road
Bethlehem, PA 18017

Phone: (610) 866-1140 Fax: (610) 758-9116 hanover@hanovertwp-nc.org

Hours
Administration

Monday - Friday: 8 am - 4 pm

Community Center
Monday - Thursday: 7 am - 10 pm
Friday: 7 am - 9 pm
Saturday: 8 am - 6 pm
Sunday: 8 am - 1 pm